Decision Memo Completed

Tennessee Valley Authority Power Project

National Forests in Mississippi Benton, Mississippi Holly Springs Ranger District

Upgrade above-ground electric power line for TVA

Location

Benton County, MS

Project timeline

1
Scoping Start
08/01/2017
2
Comment Period
08/01/2017
3
09/26/2017
4
Decision
09/2017 (Estimated)
5
Implementation
02/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Tennessee Valley Authority Power ProjectDecision Signed Date: 09/26/2017
ForestsNational Forests In Mississippi
DistrictsHolly Springs Ranger District
Legal Land DescriptionAbove-ground electric powerline
Special use management