Attach new fiber optic cable to existing power poles. Project is authorized by Homeland Security.
Location
Within the existing powerline corridor along Yeaton Spur Road and Old Highway 49 in sections 27, 28 & 34 of T1N, R12W, Forrest County, MS.
Project timeline
1
Scoping Start
07/31/2018
2
Decision
09/2018 (Estimated)
3
Implementation
10/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| AT&T Nationwide Public Safety Broadband Network Extension | Decision Signed Date: 09/25/2018 |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Not Applicable |