Decision Memo Completed

Singing River EPA Service for Billy Parker

National Forests in Mississippi George, Mississippi De Soto Ranger District

Extend overhead power to private land and future residence.

Location

Adjacent to the existing road permitted to Billy Parker, north of Jim Jam Road.

Project timeline

1
Scoping Start
09/17/2018
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Singing River EPA Service for Billy ParkerDecision Signed Date: 06/18/2019
ForestsNational Forests In Mississippi
DistrictsDe Soto Ranger District
Legal Land DescriptionT1S, R8W, Sec. 33
Special use management