Realign and reconstruct portions of the South Tank Trail adjacent to Range 49, Range 13, and Range 14 straighten blind S curves, reduce steep grades, replace culverts and redirect erosion control structures to improve drainage
Location
Camp Shelby, Forrest and Perry Counties
Project timeline
1
Scoping Start
04/29/2019
2
Decision
05/2019 (Estimated)
3
Implementation
08/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Camp Shelby South Tank Trail Realignment and Maintenance | Decision Signed Date: 05/21/2019 |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Not Applicable |