Decision Memo Completed

Camp Shelby South Tank Trail Realignment and Maintenance

National Forests in Mississippi Forrest; Perry, Mississippi De Soto Ranger District

Realign and reconstruct portions of the South Tank Trail adjacent to Range 49, Range 13, and Range 14 straighten blind S curves, reduce steep grades, replace culverts and redirect erosion control structures to improve drainage

Location

Camp Shelby, Forrest and Perry Counties

Project timeline

1
Scoping Start
04/29/2019
2
Decision
05/2019 (Estimated)
3
Implementation
08/2019 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Camp Shelby South Tank Trail Realignment and MaintenanceDecision Signed Date: 05/21/2019
ForestsNational Forests In Mississippi
DistrictsDe Soto Ranger District
Legal Land DescriptionNot Applicable
Road management