Decision Memo Cancelled

Pearl River Valley EPA Hwy. 15 Relocation

National Forests in Mississippi Stone, Mississippi De Soto Ranger District

Relocate a powerline from a 'cross-country' route to a location along a highway and county road. Abandon approx. 6.1 acres of existing r/w and authorize approx. 10.6 acres of new r/w (non-contiguous).

Location

State Highway 15 and Vestry Road

Project timeline

1
Scoping Start
12/2022 (Estimated)
2
Decision
02/2023 (Estimated)
3
Implementation
02/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsNational Forests In Mississippi
DistrictsDe Soto Ranger District
Legal Land DescriptionSections 17, 20, 21, 28 & 29, T3S, R9W