Relocate a powerline from a 'cross-country' route to a location along a highway and county road. Abandon approx. 6.1 acres of existing r/w and authorize approx. 10.6 acres of new r/w (non-contiguous).
Location
State Highway 15 and Vestry Road
Project timeline
1
Scoping Start
12/2022 (Estimated)
2
Decision
02/2023 (Estimated)
3
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Sections 17, 20, 21, 28 & 29, T3S, R9W |