Decision Memo Completed

Pearl River Valley Power EPA Powerline Amendment (Bill Anderson)

National Forests in Mississippi Perry, Mississippi De Soto Ranger District

project is to extend single phase powerline (0.81mi) (4,276ft. x 25ft.) onto private property for the purpose of serving a new member. The new service will begin on the Northeast comer of the intersection of John Bond Road and FS 330A in Perry County

Location

Perry County, West Side of John Bond Rd. Section 18, T1S, R9W

Project timeline

1
Scoping Start
07/10/2023
2
Decision
03/2024 (Estimated)
3
Implementation
04/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Pearl River Valley Power EPA Powerline Amendment (Bill Anderson)Decision Signed Date: 03/01/2024
ForestsNational Forests In Mississippi
DistrictsDe Soto Ranger District
Legal Land DescriptionSection 18, T1S, R9W
Special use management