Removal of a failing trail bridge, installation of a new bridge, and relocation of the trail to the new bridge location.
Location
South of Highway 84, as part of the Clear Springs Recreation Area. The project area can be accessed at the lower loop campground, near sites 1, 2, and 3.
Project timeline
1
Scoping Start
03/08/2024
2
Decision
08/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Forests | National Forests In Mississippi |
| Districts | Homochitto Ranger District |
| Legal Land Description | T5N, R2E, Section 2, Franklin County, MS |