This project is to install a temporary 8%u2019Wx20%u2019Lx8%u2019H wood awning with tin roof for use during dry fire exercises. An existing wall would be used to tie in the rafters and tin. Post will be 4x4, 24" in concrete, and 2x6 rafters.
Location
Camp Keller, Woolmarker Range Training Site
Project timeline
1
Scoping Start
04/09/2025
2
Decision
05/2025 (Estimated)
3
Implementation
07/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (21), 36 Cfr 220.6(E)(21) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance |
| Woolmarket Range Dry Fire Awning | Decision Signed Date: 05/16/2025 |
| Forests | National Forests In Mississippi |
| Districts | De Soto Ranger District |
| Legal Land Description | Not Applicable |