The proposed action is to restore approximately 1,000 feet of stream channel conditions and function using natural channel design techniques on a tributary between King Street and to the confluence with the Hiwassee River, by excavating and hauling.
Location
Tusquitee District Office
Project timeline
1
Scoping Start
07/12/2012
2
Comment Period
07/12/2012
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Watershed Improvements |
| Tributary to the Hiwassee River Stream Stabilization Project | Decision Signed Date: 06/06/2013 Legal Notice Date: 06/13/2013 |
| Forests | National Forests In North Carolina |
| Districts | Tusquittee Ranger District |
| Legal Land Description | Tusquitee Ranger District |