Decision Memo Completed

Progress Energy - Powerline ROW

National Forests in North Carolina Buncombe, North Carolina Pisgah Ranger District

The proposed action is to approve access for 230 volt transmission line from Enka Station to a powerplant in SE Asheville. The line crosses about 1,000 feet of NFS lands.

Location

Pisgah Ranger District

Project timeline

1
Scoping Start
03/03/2010
2
Decision
09/2010 (Estimated)
3
Implementation
03/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Progress Energy Carolinas - Enka LineDecision Signed Date: 09/30/2010
ForestsNational Forests In North Carolina
DistrictsPisgah Ranger District
Legal Land DescriptionNear Enka, NC
Land ownership management