Environmental Assessment Completed

Duke Energy - Hankin Line

National Forests in North Carolina McDowell, North Carolina Grandfather Ranger District

The proposal is to reposition the existing utility line 34 feet to the west of existing centerline, install 17 new single shaft steel poles, insulators. Old poles and materials will be removed and the corridor will be rehabilitated.

Location

Grandfather RD

Project timeline

1
Scoping Start
10/09/2012
2
Comment Period
12/05/2012
3
Decision
04/2013 (Estimated)
4
Implementation
06/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Duke Energy Hankins Transmission Line Rebuild ProjectDecision Signed Date: 04/04/2013 Legal Notice Date: 04/05/2013
ForestsNational Forests In North Carolina
DistrictsGrandfather Ranger District
Special use management