Project to replace the currently failing waste water treatment facility, move thedump station, renovate the bath house, move the host site, move potentially two camp sites, upgrade electrical and other associated tasks within the existing campgrond.
Location
Cedar Point Campground, Croatan National Forest near Cape Carteret, NC
Project timeline
1
Scoping Start
06/05/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| Cedar Point Campground Wastewater System Rehabilitation and Energy Conserva | Decision Signed Date: 07/02/2014 |
| Forests | National Forests In North Carolina |
| Districts | Croatan Ranger District |
| Legal Land Description | Not Applicable |