The proposed action is to issue a special use permit to allow expansion of the Rutherford EMC powerline right of way aerially up to 100 feet.
Location
Green Mountain Road behind Woodlawn Work Center.
Project timeline
1
Scoping Start
02/08/2016
2
Decision
05/2016 (Estimated)
3
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (8), 36 Cfr 220.6(D)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Rutherford EMC Amendment | Decision Signed Date: 05/25/2016 |
| Forests | National Forests In North Carolina |
| Districts | Grandfather Ranger District |
| Legal Land Description | Not Applicable |