The Silver Mine Group Camping facility will be decommissioned by removing buildings and structures. The Silver Mine creek will be restored by improving floodplains and bank stability and removing aquatic organism barriers
Location
Hotsprings NC
Project timeline
1
Scoping Start
03/03/2023
2
Decision
06/2023 (Estimated)
3
Implementation
07/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management; Watershed Improvements |
| Silver Mine Campground Decommissioning and Stream Restoration | Decision Signed Date: 06/30/2023 |
| Forests | National Forests In North Carolina |
| Districts | Appalachian Ranger District |
| Legal Land Description | Not Applicable |