The project seeks to to repair three sites along Bullpen Road (FS 1178) at approximately mile post 2.11, 2.74, 3.40 where storm events from 2019, 2020, and 2021 resulted in fill slope failures and damage to the Forest Service Road.
Location
Bullpen Road (FS 1178) at approximately mile post 2.11, 2.74, 3.40
Project timeline
1
Scoping Start
08/07/2023
2
Decision
08/2023 (Estimated)
3
Implementation
01/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (19), 36 Cfr 220.6(E)(19) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction |
| Bullpen Road ERFO Project | Decision Signed Date: 08/31/2023 |
| Forests | National Forests In North Carolina |
| Districts | Nantahala Ranger District |
| Legal Land Description | Not Applicable |