Removing culverts, replacing with low water crossings, and stabilizing stream bank.
Location
Curtis Creek and Mulberry Creek Watersheds
Project timeline
1
Scoping Start
02/15/2024
2
Decision
04/2025 (Estimated)
3
Implementation
10/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management; Watershed Improvements |
| Sandy Flat and Boone Fork Watershed Improvement | Decision Signed Date: 04/28/2025 |
| Forests | National Forests In North Carolina |
| Districts | Grandfather Ranger District |
| Legal Land Description | Not Applicable |