A Watershed Restoration Action Plan was created for Catheys Creek Watershed, this project is proposing to implement the actions proposed in this WRAP.
Location
Catheys Creek Watershed
Project timeline
1
Scoping Start
05/05/2023
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Decommissioning; Dispersed Recreation Mgmt.; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Catheys Creek Watershed Restoration Project Part Two | Decision Signed Date: 04/05/2025 |
| Forests | National Forests In North Carolina |
| Districts | Pisgah Ranger District |
| Legal Land Description | Not Applicable |