C-279, 280, 281, 282, 283 and 284
Location
Located approx. 6 miles south of Blue Mtn. Lake near the Blue Ball Community; FS Rd 881 is an east-west thoroughfare in the south portion of project area.
Project timeline
1
Scoping Start
10/15/2008
2
Comment Period
01/24/2009
3
Decision
03/2009 (Estimated)
4
Implementation
05/2009 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Heritage Resource Management; Minerals Or Geology Plans Of Operations; Species Population Enhancements; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Eli Branch | Decision Signed Date: 03/03/2009 Legal Notice Date: 03/05/2009 |
| Forests | Ouachita National Forest |
| Districts | Cold Springs Ranger District |
| Legal Land Description | T4N, R26W, S28, 27, 22, and 24; T4N, R25W, S 13, 18, and 17 |