The limestone glade restoration project consists of manual felling of eastern red cedar trees followed by multiple prescribed burns.
Location
Limestone Glade near Goodwater, Oklahoma
Project timeline
1
Scoping Start
03/05/2009
2
Comment Period
03/05/2009
3
Decision
05/2009 (Estimated)
4
Implementation
08/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Special Area Management |
| Limestone Glade Restoration Project | Decision Signed Date: 05/09/2009 Legal Notice Date: 05/13/2009 |
| Forests | Ouachita National Forest |
| Districts | Kiamichi Ranger District |
| Legal Land Description | T7S,R26E,Sections 20-21 |