Approximately 0.25 miles powerline construction on National Forest lands to provide additional electricity to USACE facilities.
Location
Approximately 2.5 miles West of Mountain Pine, AR.
Project timeline
1
Scoping Start
10/01/2009
2
Decision
11/2009 (Estimated)
3
Implementation
11/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Entergy Utility ROW | Decision Signed Date: 11/13/2009 |
| Forests | Ouachita National Forest |
| Districts | Womble Ranger District |
| Legal Land Description | T2S, R21W, Sec 13 |