Decision Memo Completed

Utility Relocation along US Highway 270

Ouachita National Forest Garland, Arkansas Womble Ranger District

Relocation of approximately 2 miles of existing powerline, fiberoptic cable, and waterline ROW to accommodate the AHTD widening of US Highway 270.

Location

Approximately 0.5 miles East of Crystal Springs, AR.

Project timeline

1
Scoping Start
09/28/2009
2
Decision
10/2009 (Estimated)
3
Implementation
11/2009 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Utility Line Relocation (Highway 270 Widening)Decision Signed Date: 10/19/2009
ForestsOuachita National Forest
DistrictsWomble Ranger District
Legal Land DescriptionT2S, R22W, Sec 35 and 36
Special use management