Issue road use permit to construct and maintain roads across NF to haul timber from private land.
Location
Near Tweedle Mountain approximately 2 miles north of Lodi Arkansas
Project timeline
1
Scoping Start
01/05/2010
2
Decision
08/2010 (Estimated)
3
Implementation
10/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| Tweedle Mountain Road Use Permit | Decision Signed Date: 08/02/2010 |
| Forests | Ouachita National Forest |
| Districts | Caddo Ranger District |