Project timeline
1
Scoping Start
10/12/2010
2
Decision
02/2011 (Estimated)
3
Implementation
02/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3); 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Special Use First Electric Power Line Perry Co. Rd 14 | Decision Signed Date: 02/16/2011 |
| Forests | Ouachita National Forest |
| Districts | Winona Ranger District |
| Legal Land Description | Sections 1 & 2, T3N, R18W and Sections 31 & 32, T4N, R17W; Perry Co., AR |