New 20 year lease for existing communications tower and associated equipment
Location
Approximately 7 miles east of Talihina, Oklahoma
Project timeline
1
Scoping Start
06/11/2012
2
Comment Period
06/13/2012
3
Decision
08/2012 (Estimated)
4
Implementation
11/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Verizon Communications Authorization at Sycamore Project | Decision Signed Date: 08/27/2012 Legal Notice Date: 08/30/2012 |
| Forests | Ouachita National Forest |
| Districts | Kiamichi Ranger District |
| Legal Land Description | Section 33, T4N, R23E |