AEP/SWEPCO is requesting a new SUP for the facility and equipment that is currently installed at the Poteau Mtn. Electronic Site.
Location
Poteau Mountain Electronic Site - Compartment 1218 in Mgt Area 8 (administrative sites and electronic sites)
Project timeline
1
Scoping Start
04/13/2013
2
Comment Period
04/13/2013
3
Decision
05/2013 (Estimated)
4
Implementation
06/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Special Use Permit AEP/SWEPCO | Decision Signed Date: 05/20/2013 Legal Notice Date: 05/23/2013 |
| Forests | Ouachita National Forest |
| Districts | Poteau Ranger District |