10 Year Watershed Entry Period
Location
T2N R27W Sections 13-15, 22-24, 26-27 and R26W Sections 17-18. Located SW of Harvey, AR; approximately 10 miles east of Needmore, AR.
Project timeline
1
Scoping Start
03/17/2016
2
Comment Period
08/18/2016
3
Objection Period Start
10/05/2016
4
Decision
01/2017 (Estimated)
5
Implementation
02/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Dispersed Recreation Mgmt.; Species Habitat Improvements; Heritage Resource Management; Noxious Weed Treatments; Species Population Enhancements; Road Maintenance; Road Improvements/Construction; Scenery Management; Timber Sales (Salvage); Travel Management; Timber Sales (Green); Watershed Improvements |
| Holly Mountain Decision Notice | Decision Signed Date: 01/03/2017 |
| Forests | Ouachita National Forest |
| Districts | Cold Springs Ranger District |
| Legal Land Description | Not Applicable |