Environmental Assessment Completed

Brier Creek Watershed

Ouachita National Forest Polk, Arkansas Mena Ranger District

The Mena-Oden Ranger District proposes to implement management activities identified in to meet the needs for Brier Creek watershed project area. The intent of these activities is to move the project area toward desired conditions in the Forest Plan.

Location

Compartment 860,886,887,907,908,909

Project timeline

1
Scoping Start
12/01/2016
2
Comment Period
06/22/2017
3
Decision
08/2017 (Estimated)
4
Implementation
09/2017 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage); Travel Management; Timber Sales (Green); Watershed Improvements
Brier Creek WatershedDecision Signed Date: 08/25/2017
ForestsOuachita National Forest
DistrictsMena Ranger District
Legal Land DescriptionNot Applicable
Wildlife, fish, rare plantsForest productsVegetation management (other than forest products)Fuels managementWatershed managementRoad management