Removal of 12'X20'ft. slab and existing culverts. Culverts will be replaced back into the stream line covered with compacted material and 7 1/2" of concrete.
Location
Post Mountain
Project timeline
1
Scoping Start
08/04/2017
2
Decision
08/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction |
| F.S. Rd. 6016 Post Mountain Slab Repair | Decision Signed Date: 08/24/2017 |
| Forests | Ouachita National Forest |
| Districts | Kiamichi Ranger District |
| Legal Land Description | T4N, R25E, Sec.31 |