Watershed entry including timber harvest, prescribed burning, wildlife enhancement activities.
Location
Approx. 10 miles north of Mount Ida, AR
Project timeline
1
Scoping Start
03/08/2019
2
Comment Period
09/01/2019
3
Decision
10/2019 (Estimated)
4
Implementation
01/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction; Travel Management; Timber Sales (Green); Watershed Improvements |
| Fulton Branch | Decision Signed Date: 10/28/2019 |
| Forests | Ouachita National Forest |
| Districts | Womble Ranger District |
| Legal Land Description | Not Applicable |