The addition of two new water control structures (consisting of screw gates with 12" steel pipes and wire mesh panels) within Red Slough Wildlife Management Area to facilitate drainage and allow for water level manipulation within Units 30W and 31.
Location
Four miles west Tom, Oklahoma.
Project timeline
1
Scoping Start
04/29/2019
2
Decision
12/2019 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Species Population Enhancements |
| Red Slough Water Control Structure Installation | Decision Signed Date: 12/16/2019 |
| Forests | Ouachita National Forest |
| Districts | Kiamichi Ranger District |
| Legal Land Description | A portion of Section 36, Township 9 South, Range 25 East of the I.B.M. |