Choctaw Electric Coop., Inc. requests authorization to upgrade transmission capacity within an existing right of way across National Forest System (NFS) lands on the Ouachita National Forest.
Location
Hochatown, Oklahoma
Project timeline
1
Scoping Start
11/22/2022
2
Decision
12/2022 (Estimated)
3
Implementation
12/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Choctaw Electric Cooperative, Inc. Power Line Upgrades Near Government Spring | Decision Signed Date: 12/16/2022 |
| Forests | Ouachita National Forest |
| Districts | Kiamichi Ranger District |
| Legal Land Description | Not Applicable |