Project timeline
1
Scoping Start
11/22/2022
2
Decision
01/2023 (Estimated)
3
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Windstream Fiber Optic Cable Install AR188 | Decision Signed Date: 01/27/2023 |
| Forests | Ouachita National Forest |
| Districts | Womble Ranger District |
| Legal Land Description | T1S R23W SEC 28, 31-33; T1S R24W SEC 36; T2S R23W SEC 5-6; T2S R24W SEC 1-4, 9 |