Decision Memo Completed

Windstream Fiber Optic Cable Install AR188

Ouachita National Forest Montgomery, Arkansas Womble Ranger District

Fiber optic installation within an existing designated corridor along Arakansas Highway 188

Location

3.4 miles northwest of Mount Ida, Arkansas

Project timeline

1
Scoping Start
11/22/2022
2
Decision
01/2023 (Estimated)
3
Implementation
02/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Windstream Fiber Optic Cable Install AR188Decision Signed Date: 01/27/2023
ForestsOuachita National Forest
DistrictsWomble Ranger District
Legal Land DescriptionT1S R23W SEC 28, 31-33; T1S R24W SEC 36; T2S R23W SEC 5-6; T2S R24W SEC 1-4, 9
Special use management