Install powerline to provide serivce to a private inholding surronded by National Forest System land.
Location
7.2 miles southwest of Black Springs
Project timeline
1
Scoping Start
12/19/2022
2
Decision
08/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Entergy Powerline Install on Forest Service Road 99 | Decision Signed Date: 08/02/2023 |
| Forests | Ouachita National Forest |
| Districts | Caddo Ranger District |
| Legal Land Description | T4S R26W SEC 27-29 |