The Caddo-Womble Ranger District is proposing to grant a speical use road permit to Kingwood Forestry to construct a .3-mile temporary road to access some timber harvest areas. The temporary road is an old existing one used in the past.
Location
The project are is located 7.4 miles west of Hot Springs.
Project timeline
1
Scoping Start
01/13/2025
2
Decision
03/2025 (Estimated)
3
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (12), 36 Cfr 220.6(E)(12) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forest Serivce Road C02E Special Use Project | Decision Signed Date: 03/25/2025 |
| Forests | Ouachita National Forest |
| Districts | Caddo Ranger District |
| Legal Land Description | Not Applicable |