Windstream Communications, Inc. is requesting the authorization of installing approximatetly 1,702 feet of underground copper cable on the National Forest System lands to provide telecommunications services.
Location
The project is located 9 miles southwest of Black Springs Coummnity
Project timeline
1
Scoping Start
02/28/2025
2
Decision
03/2025 (Estimated)
3
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Ouachita National Forest |
| Districts | Caddo Ranger District |
| Legal Land Description | Not Applicable |