This project proposes to manipulate northern hardwood forest vegetation composition and structure, and road access to manage the Fishel area closer to desired forest conditions as defined in the 2004 Chequamegon-Nicolet LRMP.
Location
Ten miles northeast of Eagle River
Project timeline
1
NOI in Federal Register
03/22/2006
2
DEIS NOA in Federal Register
05/25/2007
3
FEIS NOA in Federal Register
03/07/2008
4
Decision
02/2008 (Estimated)
5
Implementation
08/2008 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Forest Vegetation Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage); Timber Sales (Green); Watershed Improvements |
| Fishel Vegetation and Transportation Management Project | Decision Signed Date: 02/22/2008 Legal Notice Date: 03/08/2008 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | T40N R11E Sec. 1, 12, 13, 14, 23, 24; T41N R11E Sec. 25, 36; T40N R12E Sec. 1-12, 17, 18; T41N R12E Sect. 1, 2, 11-17, 19-36; T42N R12E Sec. 36; T41N R13E Sec. 5-10, 15-21, 29-32; T42N R13E Sec. 31 |