Improve/construct and designate existing roads and trails for ATV use. The new trail would go from Mountain Lakes Road to the Nicolet State Trail.
Location
Mountain Lake Road
Project timeline
1
Scoping Start
06/17/2010
2
Decision
08/2010 (Estimated)
3
Implementation
08/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Mountain Lakes Road to Nicolet State Trail ATV Connector | Decision Signed Date: 08/17/2010 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Lakewood-Laona Ranger District |
| Legal Land Description | T32N, R16E, Sections 28, 29, 32, and 33 |