Removal of the 150-foot long dike and dam (whistle tube), and restoration of the tributary to a natural stream.
Location
Approximately four miles southwest of Alvin, and 16 miles east of Eagle River, Wisconsin.
Project timeline
1
Scoping Start
02/09/2010
2
Decision
07/2010 (Estimated)
3
Implementation
06/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Alvin Creek Water Control Structure Removal | Decision Signed Date: 07/07/2010 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | T40N, R13E, Section 16 |