The current trail would be relocated to provide a safer trail for snowmobilers by reducing hills and curves in the trail.
Location
Military Road
Project timeline
1
Scoping Start
02/20/2013
2
Comment Period
02/24/2013
3
Decision
07/2013 (Estimated)
4
Implementation
08/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| Military Road Snowmobile Relocation | Decision Signed Date: 07/23/2013 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District |
| Legal Land Description | T40N, R11E, Sections 35 and 36; T39N, R11E, Sections 1, 2, 11-14. |