Authorization to convert a portion of an existing distribution line from overhead to underground and install a new section of underground distribution line along Forest Circle Drive.
Location
1/4 mile west of Moose Lake along Forest Circle Drive
Project timeline
1
Scoping Start
09/05/2014
2
Decision
12/2014 (Estimated)
3
Implementation
12/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Jump River Electric Rebuild Project | Decision Signed Date: 12/08/2014 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Great Divide Ranger District |
| Legal Land Description | T41N R6W S24 |