The Cooperative mistakenly installed a generator at the Ino Tower facility without approval. Proposal is to amend an existing permit to allow for the generator and associated equipment within the fenced area. Footprint (fenced area) remains the same.
Location
Eight miles east of Iron River, WI.
Project timeline
1
Scoping Start
01/07/2015
2
Decision
04/2015 (Estimated)
3
Implementation
04/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Chequamegon Communications Cooperative Inc. Ino Tower Generator Project | Decision Signed Date: 04/10/2015 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Washburn Ranger District |