Decision Memo Completed

WI Public Service 2016 Electric Reliability Projects, part 2

Chequamegon-Nicolet National Forest Oconto, Wisconsin Chequamegon / Nicolet National Forest All Units

Installation of approx. 8,448 feet of underground electric line within the existing road right-of -way on Oconto Hwy T, old Hwy 32,and Tar Dam Road.

Location

T31N, R16E, Section 3; T32N, R15E, Section 8; T32N, R16E, Section 21; Oconto County, Wisconsin

Project timeline

1
Scoping Start
06/23/2016
2
Decision
06/2017 (Estimated)
3
Implementation
06/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
WI Public Service 2016 Electric Reliability Projects, part 2Decision Signed Date: 06/08/2017
ForestsChequamegon / Nicolet National Forest
DistrictsLakewood-Laona Ranger District
Legal Land DescriptionNot Applicable
Special use management