Decision Memo Completed

Morgan Falls Trail Realignment and Reconstruction

Chequamegon-Nicolet National Forest Ashland, Wisconsin Great Divide Ranger District

Flood damage repair, reconstruction and realignment, including trailhead parking area relocation and expansion, trail segment construction, reconstruction, and repair, construction and installation of boardwalk over Morgan Creek and more

Location

Morgan Falls/St. Peters Dome Trailhead

Project timeline

1
Scoping Start
01/06/2017
2
Decision
07/2017 (Estimated)
3
Implementation
09/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
Morgan Falls Trail Realignment and ReconstructionDecision Signed Date: 07/21/2017
ForestsChequamegon / Nicolet National Forest
DistrictsGreat Divide Ranger District
Legal Land DescriptionT45N R4W Section 30
Recreation management