To replace about 3,000 ft of existing overhead powerline with a new underground line within the existing utility corridor. New buried cable would be within the existing right-of-way. Proposal includes the removal of overhead supporting infrastructure
Location
Near Marengo Lake Road (FR 384), Town of Grandview, the section runs between FR 202 and FR 384.
Project timeline
1
Scoping Start
03/16/2018
2
Decision
08/2018 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Bayfield Electric SUP 2018 | Decision Signed Date: 08/20/2018 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Great Divide Ranger District |
| Legal Land Description | T 44 North, R 5 West, Sec 4, Bayfield County, WI |