Xcel Energy is planning to rebuild their W3477 electric transmission line, a portion of which is located on National Forest. The line would be the same voltage (69 kV), but taller poles would be installed to meet current line requirements.
Location
Transmission line is located in Price and Taylor Counties with the portion on National Forest being on the eastern side of the Taylor County portion of the Medford-Park Falls Ranger District.
Project timeline
1
Scoping Start
05/30/2019
2
Decision
06/2019 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Xcel Energy W3477 Electric Line Rebuild | Decision Signed Date: 06/21/2019 |