An amendment to the Special Use Permit to replace existing overhead powerline with a new underground line within the existing utility corridor right-of-way. Proposal includes the removal of overhead supporting infrastructure.
Location
Multiple locations on Great Divide and Washburn Ranger Districts
Project timeline
1
Scoping Start
08/01/2019
2
Decision
09/2019 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 2019 Bayfield Electric Line Burial | Decision Signed Date: 09/27/2019 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Great Divide Ranger District; Washburn Ranger District |
| Legal Land Description | Not Applicable |