An amendment to the Special Use Permit to relocate an existing powerline that is being affected by high water in Pigeon Lake with a new underground line along FR228. Proposal includes the removal of old infrastructure.
Location
Bayfield County T45N, R8W, Sections 26 and 35
Project timeline
1
Scoping Start
07/22/2019
2
Decision
07/2019 (Estimated)
3
Implementation
08/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Bayfield Electric Pigeon Lake Line Burial 2019 | Decision Signed Date: 07/31/2019 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Washburn Ranger District |
| Legal Land Description | Not Applicable |