Fiberoptic cable will be installed along Forest Road 308 in three locations in the existing , cleared right-of-way using a vibratory plow and directional bore.
Location
T40N R5W Section 14, T40N R5W Section 13, and T40N R4W Section 18
Project timeline
1
Scoping Start
06/09/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| CenturyTel Fiberoptic Installation 2020 Along Forest Road 308 | Decision Signed Date: 10/15/2020 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Great Divide Ranger District |
| Legal Land Description | Not Applicable |