Decision Memo Completed

CenturyTel Fiberoptic Installation 2020 Along Forest Road 308

Chequamegon-Nicolet National Forest Sawyer, Wisconsin Great Divide Ranger District

Fiberoptic cable will be installed along Forest Road 308 in three locations in the existing , cleared right-of-way using a vibratory plow and directional bore.

Location

T40N R5W Section 14, T40N R5W Section 13, and T40N R4W Section 18

Project timeline

1
Scoping Start
06/09/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
CenturyTel Fiberoptic Installation 2020 Along Forest Road 308Decision Signed Date: 10/15/2020
ForestsChequamegon / Nicolet National Forest
DistrictsGreat Divide Ranger District
Legal Land DescriptionNot Applicable
Special use management