USFS and WGNHS propose to study the hydrogeology of the North Fork Yellow River Watershed near the Bend ore deposit in Taylor County to better understand the geology and groundwater connections in this area.
Location
T33N, R2W, Sections 34 & 35; T32N, R2W, Sections 2 & 3
Project timeline
1
Scoping Start
03/30/2021
2
Decision
07/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Taylor County Hydrogeology Survey | Decision Signed Date: 07/16/2021 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Medford-Park Falls Ranger District |
| Legal Land Description | Not Applicable |