Project is located along roads on the Nicolet side of the forest. WPS is maintaining and upgrading their lines.
Location
Nicolet side of the forest.
Project timeline
1
Scoping Start
06/24/2021
2
Decision
07/2021 (Estimated)
3
Implementation
08/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| 2021 WPS Nicolet | Decision Signed Date: 07/12/2021 |
| Forests | Chequamegon / Nicolet National Forest |
| Districts | Eagle River-Florence Ranger District; Lakewood-Laona Ranger District |
| Legal Land Description | Not Applicable |